Comelli multi-tenanted factories
Project overview
Having successfully dealt with us in the past on other commercial and industrial projects, Eddy approached us again with an idea for a multi-tenanted factory complex.
We assisted Eddy when designing the architectural elements, such as alternate cladding and glazing. He was keen for the building to have a hidden roofline, so parapets were included in the design.
- $250K*
- 19m x 16m and 19m x 17m
- 24 weeks
- Civil engineer
- Third-party installer
- Third-party architect
- 3D structural model
- Fabricated hot dipped galvanized steel package
- Purlins and girts
- Roller shutters
- Insulation and roof safety mesh
- Toe flashing
- Parapet
- Box gutters
- Horizontal and vertical cladding
- 1m retaining wall
- Roof and wall cladding
- Guttering and downpipe system
- Daylesford, Victoria
*All prices are an indication only and are subject to change at any time due to steel prices. Prices also do not include site preparation or installation costs.
Challenges and solutions
Eddy had pre-engineered drawings done before approaching us, so he provided these to us to work from. However, the drawings didn’t consider the retaining walls that were required. We came up with an innovative solution and collaborated with the engineer to incorporate this into the final design.
“Central Steel Build were great to deal with throughout the whole building process. They were helpful and accommodating. We would not hesitate in recommending them.”