Western Region Waste and Recycling combined office and warehouse
Project overview
The client approached us direct to build a 3700m2 recycling transfer station and office facility to work with traffic flow and height requirements whilst still maintaining an economical build cost.
He came to us with a rough size and a clear idea of what he wanted at the end of the project. We then came up with a design that fulfilled his requirements and made the building very economical.
Project value:
- $900K-1.3M*
On-site build time:
- 10 weeks
Project collaborators:
- Draftsperson
- Structural engineer
- Geotech consultant
- Fire engineer
- Slab concreter
- Builder for fit-out works
Job site location:
- Maddingley, Victoria
Our scope and build details:
- Structural steel drawings, engineering certification and computations.
- Structural concrete engineering including slab and office slab design.
- 3D structural/shop steel drawings.
- Fabricated hot dipped galvanised steel package.
- Purlins and girts.
- External steel cladding.
- Industrial fire egress compliant access doors.
- Guttering and above ground rainwater systems.
- Mezzanine floor.
- Multiple sliding doors.
- Attached office complex packages including steel and roof.
- Cantilever canopies.
*All prices are an indication only and are subject to change at any time due to steel prices. Prices also do not include site preparation or installation costs.
Challenges and solutions
Our client required a certain clearance height so his machinery could function inside, along with a requirement for a large number of entry and exit doors on both sides of the building.
We needed to test some concepts and studies on clearance heights as well as establish exactly what clearance height his specified machinery needed. Equipped with this essential information, we proceeded to work from the specs to determine an eave height for the structure. In regards to the door requirements, we researched the idea of roller shutters but ended up implementing a sliding door system with a removable ‘centre’ sliding door guide so there were no obstacles for Western Region Recycle and Waste Centre’s clients to hit when driving into the building.